Relating risk to project performance in Indonesian building contracts

Wiguna, I P A and Scott, S (2006) Relating risk to project performance in Indonesian building contracts. Construction Management and Economics, 24(11), pp. 1125-1135. ISSN 1466433X

Abstract

A construction project is unique, specific and dynamic, and therefore projects have different levels and combinations of risks, different responses are taken to minimise those risks and different consequences affect project performance. The primary aim of this study was to analyse the impacts of perceived project risk on project performance. A path model was developed and path analysis was used to determine the relationships between risk and performance. The main survey was predominantly based on a series of interviews with project managers. A total of 22 building projects under construction were surveyed; however, only 13 projects used an 'S' curve to monitor their project performance. The study focused on these 13 projects and found that perceived project risk had a direct negative effect on monthly progress achievement, while monthly progress had a direct positive impact on schedule performance. Although project risk had no direct effect on schedule performance, this was influenced indirectly with monthly progress as the mediator between them. These findings indicate that the higher the project risk in a project, the greater the negative impact on monthly progress, and consequently the worse the schedule performance will be.

Item Type: Article
Uncontrolled Keywords: building project; path analysis; project delay; project performance; risk management
Date Deposited: 11 Apr 2025 14:47
Last Modified: 11 Apr 2025 14:47