The integration of CPM and material management in project management

Shtub, A (1988) The integration of CPM and material management in project management. Construction Management and Economics, 6(4), pp. 261-272. ISSN 01446193

Abstract

The problem of scheduling a project for which expensive, long-lead inventory items have to be ordered from outside vendors is addressed. A logic aimed at minimizing the cost of such projects is presented along with an illustrative example. The logic is based on adding a material management module to the CPM analysis, evaluating the feasibility of the CPM schedule, and rescheduling the project in case long-lead items make the schedule generated by CPM infeasible. An attempt to integrate CPM and material management in a large-scale construction project is reported and possible extensions of this research are suggested.