Optimizing time, cost and quality in multi-mode resource-constrained project scheduling

Kannimuthu, M; Raphael, B; Palaneeswaran, E and Kuppuswamy, A (2019) Optimizing time, cost and quality in multi-mode resource-constrained project scheduling. Built Environment Project and Asset Management, 9(1), pp. 44-63. ISSN 2044-124X

Abstract

Purpose: The purpose of this paper is to develop a framework to optimize time, cost and quality in a multi-mode resource-constrained project scheduling environment. Design/methodology/approach: A case study approach identified the activity execution modes in building construction projects in India to support multi-mode resource-constrained project scheduling. The data required to compute time, cost and quality of each activity are compiled from real construction projects. A binary integer-programming model has been developed to perform multi-objective optimization and identify Pareto optimal solutions. The RR-PARETO3 algorithm was used to identify the best compromise trade-off solutions. The effectiveness of the proposed framework is demonstrated through sample case study projects. Findings: Results show that good compromise solutions are obtained through multi-objective optimization of time, cost and quality. Research limitations/implications: Case study data sets were collected only from eight building construction projects in India. Practical implications: It is feasible to adopt multi-objective optimization in practical construction projects using time, cost and quality as the objectives; Pareto surfaces help to quantify relationships among time, cost and quality. It is shown that cost can be reduced by increasing the duration, and quality can be improved only by increasing the cost. Originality/value: The use of different activity execution modes compiled from multiple projects in optimization is illustrated, and good compromise solutions for the multi-mode resource-constrained project scheduling problems using multi-objective optimization are identified.

Item Type: Article
Uncontrolled Keywords: construction quality assessment system; global optimization; multi-criterion decision-making; multi-mode resource-constrained project scheduling; multi-objective optimization; time–cost–quality
Date Deposited: 11 Apr 2025 13:55
Last Modified: 11 Apr 2025 13:55