Analysis of schedule deviations in road construction projects and the effects of project physical characteristics

Mahamid, I (2017) Analysis of schedule deviations in road construction projects and the effects of project physical characteristics. Journal of Financial Management of Property and Construction, 22(2), pp. 192-210. ISSN 1366-4387

Abstract

A study on the main factors affecting time deviation in road construction projects reveals the top five factors: political situation, payments delay by the owner, lack of coordination between construction parties, frequent change orders and unexpected ground condition and terrain.

Item Type: Article
Uncontrolled Keywords: scheduling; time overrun; deviation; road construction; physical characteristics