Liu, W; Zhang, J; Qu, C and Zhang, H (2024) Performance of priority rules for finance-based and resource-constrained project scheduling heuristics. Journal of Construction Engineering and Management, 150(6), ISSN 0733-9364
Abstract
Over the years, the finance-based and resource-constrained project scheduling problem (FBRCPSP) has been aimed at scheduling activities and offsetting the capital gap without exceeding credit and renewable resource limits in capital-driven construction projects. However, the heuristics proposed for the FBRCPSP in previous studies neglected to focus on identifying efficient priority rules, which are understandable and intuitive for construction practitioners with different roles. Accordingly, this study explores efficient priority rules and evaluates their performance according to modified serial and parallel schedule generation scheme heuristics for the FBRCPSP. First, 11 priority rules that cover the project network, schedule, activity, and resource information are introduced, and three priority rules related to activity information are designed. Second, the two priority rule-based heuristics are applied in an example to generate multiple project schedules according to the different combinations of priority rules and heuristics. Furthermore, the performance of priority rules is tested on the metrics of project duration and profit through numerical experiments. The results show that the priority rules of the latest start time, latest finish time, and old great rank positional weight are the three best priority rules in general. Additionally, the priority rules evenly present more stable and superior results than those obtained by other priority rules for the different levels of weekly fixed overhead cost and the scenarios of contract terms. Based on the intuitive heuristics, the selected efficient priority rules assist contractors in deciding which priority rule should be applied in practice, and project managers can employ an effective priority rule to establish a baseline schedule in the initial project phase and quickly adjust the plan when it becomes infeasible for project execution.
Item Type: | Article |
---|---|
Uncontrolled Keywords: | finance-based projects; heuristic methods; priority rules; project scheduling |
Date Deposited: | 11 Apr 2025 19:50 |
Last Modified: | 11 Apr 2025 19:50 |