González-Cruz, M C; Ballesteros-Pérez, P; Lucko, G and Zhang, J X (2022) Critical duration index: Anticipating project delays from deterministic schedule information. Journal of Construction Engineering and Management, 148(11), ISSN 0733-9364
Abstract
Classical scheduling techniques are well-known to underestimate the average project duration, yet they remain widely used in practice due to their simplicity. In this paper, the new Critical Duration Index (CDI) is proposed. This index indirectly allows anticipation for the probability of a project ending late, as well as the average project duration extension compared with a deterministic project duration estimate. The accuracy of two simple regression expressions that use the CDI was tested on two representative data sets of 4,100 artificial and 108 empirical (real) projects. Results show that these regression expressions outperformed the only alternative index found in the literature. Besides allowing enhanced forecasting possibilities, calculating the CDI only requires basic scheduling information that is available at the planning stage. It can thus be easily adopted by project managers to improve their project duration estimates over prior deterministic techniques.
Item Type: | Article |
---|---|
Uncontrolled Keywords: | delays; forecasting; project; regression; scheduling |
Date Deposited: | 11 Apr 2025 19:49 |
Last Modified: | 11 Apr 2025 19:49 |