El-Rayes, K (2001) Object-oriented model for repetitive construction scheduling. Journal of Construction Engineering and Management, 127(3), pp. 199-205. ISSN 0733-9364
Abstract
This paper presents the development of an object-oriented model for scheduling of repetitive construction projects such as high-rise buildings, housing projects, highways, pipeline networks, bridges, tunnels, railways, airport runways, and water and sewer mains. The paper provides an overview of the analysis, design, and implementation stages of the developed object-oriented model. These stages are designed to provide an effective model for scheduling repetitive construction projects and to satisfy practical scheduling requirements. The model incorporates newly developed procedures for resource-driven scheduling of repetitive activities, optimization of repetitive construction scheduling, and integration of repetitive and nonrepetitive scheduling techniques. The model is named LSCHEDULER and is implemented as a windows application that supports user-friendly interface including menus, dialogue boxes, and windows. LSCHEDULER can be applied to perform regular scheduling as well as optimized scheduling. In optimized scheduling, the model can assist in identifying an optimum crew utilization option for each repetitive activity in the project that provides a minimum duration or cost for the scheduled repetitive construction project.
Item Type: | Article |
---|---|
Date Deposited: | 11 Apr 2025 19:40 |
Last Modified: | 11 Apr 2025 19:40 |