Planning in construction: Longitudinal study of pre-contract planning model demonstrates reduction in project cost and schedule growth

Lines, B C; Sullivan, K T; Hurtado, K C and Savicky, J (2015) Planning in construction: Longitudinal study of pre-contract planning model demonstrates reduction in project cost and schedule growth. International Journal of Construction Education and Research, 11(1), pp. 21-39. ISSN 1557-8771

Abstract

Planning is known to enhance construction project performance in terms of cost, schedule, and quality. Yet, project teams oftentimes do not incorporate effective planning methodologies, typically citing a lack of time or capability to conduct detailed planning. This article proposes a brief yet rigorous project planning method, known as the pre-contract planning model, which is uniquely implemented between the owner and selected contractor project teams prior to contract award with the intent of increasing project team alignment and facilitating greater risk transfer from owner to contractor. Results from a multi-case longitudinal study documented the impact of the pre-contract planning model in terms of three success criteria: cost growth, schedule growth, and owner satisfaction, where cost and schedule growth were measured as percent increase of initial contract values. Projects that implemented the pre-contract planning model were compared with a control group that operated via a traditional project delivery process where the selected contractor directly proceeded to contract award without a formal planning process. Analysis revealed that the pre-contract planning model reduced cost and schedule growth by as much as 54% and 70% percent, respectively, indicating that pre-contract planning may be a viable planning mechanism to be implemented in the construction industry.;  Planning is known to enhance construction project performance in terms of cost, schedule, and quality. Yet, project teams oftentimes do not incorporate effective planning methodologies, typically citing a lack of time or capability to conduct detailed planning. This article proposes a brief yet rigorous project planning method, known as the pre-contract planning model, which is uniquely implemented between the owner and selected contractor project teams prior to contract award with the intent of increasing project team alignment and facilitating greater risk transfer from owner to contractor. Results from a multi-case longitudinal study documented the impact of the pre-contract planning model in terms of three success criteria: cost growth, schedule growth, and owner satisfaction, where cost and schedule growth were measured as percent increase of initial contract values. Projects that implemented the pre-contract planning model were compared with a control group that operated via a traditional project delivery process where the selected contractor directly proceeded to contract award without a formal planning process. Analysis revealed that the pre-contract planning model reduced cost and schedule growth by as much as 54% and 70% percent, respectively, indicating that pre-contract planning may be a viable planning mechanism to be implemented in the construction industry.;

Item Type: Article
Uncontrolled Keywords: planning; construction; change order; project cost; schedule growth; success factors; contractors; project management; construction costs; construction contracts; cost reduction
Date Deposited: 11 Apr 2025 16:24
Last Modified: 11 Apr 2025 16:24