Risk management for asphalt road construction and maintenance under performance-based contracts

Hashem M. Mehany, M S and Guggemos, A (2015) Risk management for asphalt road construction and maintenance under performance-based contracts. International Journal of Construction Education and Research, 11(4), pp. 292-315. ISSN 1557-8771

Abstract

Contractors have been the main risk bearers in most road construction and maintenance projects, especially when they are working under higher-risk delivery systems such as Performance Based Contracts (PBC), where the contractors are more likely to be responsible for both the construction and maintenance of the road for a certain warranty period. This research identified and analyzed the risks that the contractor is subject to under PBCs for hot mix asphalt (HMA) road construction and maintenance projects. The study used a mixed methods research design and was divided into three phases. In the first phase, employing a detailed literature review along with industry interviews, twenty-nine risks were identified in the construction and maintenance phases. In the second phase, risk severity rankings were calculated using probability and impact data that was collected from several contractors and a state agency. In the final phase, a correlation analysis was conducted. The results of this analysis will enable contractors to make adjustments and modifications to address the highest and most severe risks.;Contractors have been the main risk bearers in most road construction and maintenance projects, especially when they are working under higher-risk delivery systems such as Performance Based Contracts (PBC), where the contractors are more likely to be responsible for both the construction and maintenance of the road for a certain warranty period. This research identified and analyzed the risks that the contractor is subject to under PBCs for hot mix asphalt (HMA) road construction and maintenance projects. The study used a mixed methods research design and was divided into three phases. In the first phase, employing a detailed literature review along with industry interviews, twenty-nine risks were identified in the construction and maintenance phases. In the second phase, risk severity rankings were calculated using probability and impact data that was collected from several contractors and a state agency. In the final phase, a correlation analysis was conducted. The results of this analysis will enable contractors to make adjustments and modifications to address the highest and most severe risks.;

Item Type: Article
Uncontrolled Keywords: risk management; asphalt contractors; asphalt road maintenance; asphalt road construction; performance based contracts; asphalt; highway construction; repair & maintenance; construction contracts
Date Deposited: 11 Apr 2025 16:24
Last Modified: 11 Apr 2025 16:24